WHEN PRODUCTION COMES TO A HALT

When critical equipment fails, every hour matters.

In the spring of 2025, Ahlstrom’s Rhinelander Paper Mill faced a major disruption when its steam turbine and line shaft driving the wet end and dryers of Paper Machine 6 (R6) failed beyond repair. The legacy system dated back to the 1940s, and with no direct replacement readily available, Ahlstrom needed more than a repair. It needed a modern path forward that could restore production quickly while reducing reliance on aging infrastructure.

Traditional replacement solutions carried lead times of more than 40 weeks, while the mill’s priority was clear: restore production as quickly as possible.

RESPONDING WHEN EVERY DAY COUNTS

The morning after the failure, Ahlstrom brought Werner onsite with Rockwell Automation to assess the situation and determine how to get R6 operating again.

The teams evaluated multiple approaches, including rebuilding the existing turbine and line shaft, developing a hybrid solution, or transitioning to a sectionalized drive system. With time as the most critical factor, they chose a path that would not simply replace the failed equipment but modernize how the machine was driven.

From there, Werner, Rockwell Automation, and Ahlstrom moved quickly.

MODERNIZING UNDER PRESSURE

The solution replaced the legacy turbine-driven system with modern motors, variable frequency drives, motor control centers, and supporting electrical infrastructure.

Rather than recreating the decades-old mechanical system, the team used the outage to transition R6 to a more flexible, electrically driven architecture.

But equipment was only part of the challenge. R6 did not have the existing infrastructure needed to support a modern drive system. Werner helped coordinate electrical design and equipment selection while also providing network and server upgrades, programming, motors, transformers, drive cable, and other critical components.

Instead of following a traditional sequential project timeline, the team worked in parallel. Drives and other equipment were ordered while electrical infrastructure, specifications, and software were still being developed. That approach helped shorten the overall project timeline while keeping engineering, installation, and startup moving toward the same goal.

A PLAN PUT INTO ACTION

RAPID ASSESSMENT & PLANNING Werner and Rockwell Automation quickly joined Ahlstrom onsite to assess the failure, evaluate potential solutions, and establish a path back to production.
ELECTRICAL MODERNIZATION The team transitioned R6 from its legacy turbine and line-shaft system to a modern sectionalized drive system using motors, VFDs, MCCs, and supporting electrical equipment.
NETWORK & CONTROLS Werner supported network and server upgrades, controls programming, and the infrastructure required to bring the new drive system online. Additional network improvements were also completed during the outage.
PROJECT COORDINATION Dedicated project managers, daily meetings, transparent communication, and close coordination between Ahlstrom, Werner, Rockwell Automation, and installation partners helped teams make decisions quickly and keep work moving.

BACK TO MAKING PAPER IN 17 WEEKS

In mid-August, approximately 17 weeks after the initial failure, R6 produced saleable paper again.

The result represented more than a return to production. Within the early weeks of operation, the modernized machine was already achieving new production records, demonstrating that the accelerated project did not require Ahlstrom to sacrifice long-term performance for speed.

What began as an unexpected equipment failure became an opportunity to replace aging infrastructure with a modern drive platform designed to better support the mill moving forward.

PARTNERSHIP DRIVES THE TIMELINE

Executing a project of this scale on an accelerated timeline required more than equipment availability. It required trust.

Ahlstrom, Werner, and Rockwell Automation operated as one team, holding daily meetings, sharing information openly, and making decisions as the project evolved. Werner supported electrical design during the quoting process, equipment was ordered before every design detail was complete, and teams adapted quickly when circumstances changed.

That willingness to work differently helped turn a timeline traditionally measured in 40 weeks into a 17-week path back to production.

BUILT FOR WHAT COMES NEXT

For Ahlstrom, the project corrected a critical failure which resulted in replacing decades-old equipment with a modern electrical, controls, and network platform.

For others this demonstrates a broader lesson for manufacturers operating aging equipment: modernization does not have to mean replacing everything at once. With the right plan, facilities can address immediate priorities while creating a stronger foundation for future upgrades, greater connectivity, and long-term reliability.

For Werner, partnership means helping customers understand that path, bringing the right resources together, and staying involved from initial assessment through implementation and startup.

The result was not simply getting R6 running again. It was helping Ahlstrom move forward with a more modern foundation for the future.

“
“From day 0 all the way through, Werner supported us at every step of the way, from equipment design and specifications to expediting equipment lead times, pre-installation support, programming, and startup!”
CHRIS REDMOND PROJECT ENGINEER AHLSTROM
”